November 3, 2010
We are at the end of week two for The Flood House rehab, and so far, we’re pretty much on-schedule and a bit ahead of budget… After completing all the demo, rough plumbing, rough electrical and inspections during week one, we’ve spent week two doing mold remediation, installing insulation, and hanging/finishing drywall. The mold remediation […]
Read the full article →
September 17, 2010
We finished the rehab on The Haggle House earlier this week (total of three days), got some appliances installed yesterday, and are finishing up the cleaning today. We’re planning to start looking for renters this weekend… This was our smallest and quickest rehab yet (as it’s our first rental property and the goal wasn’t to […]
Read the full article →