November 10, 2010
We are at the end of week three for The Flood House rehab, and I’m happy to report that we’re still on-schedule and still ahead of budget…
This week we completed the drywall installation, hung the doors, installed the baseboards, replaced a bunch of windows, painted the interior and made some repairs to the exterior trim. [...]
Read the full article →
November 3, 2010
We are at the end of week two for The Flood House rehab, and so far, we’re pretty much on-schedule and a bit ahead of budget…
After completing all the demo, rough plumbing, rough electrical and inspections during week one, we’ve spent week two doing mold remediation, installing insulation, and hanging/finishing drywall. The mold remediation [...]
Read the full article →